CD4CDM PROJECT IN SURINAME
Training workshop on CDM project development in Surinam

18 – 20 June 2008
Paramaribo, Suriname
 

Agenda

 

18 June 2008

 

8.30 – 8.30 Registration
8.30 – 8.45 Welcome, objectives, agenda

8.45 – 9.15

CDM summary

Brief summary of the National Workshop of 23 and 24 April.

Institutional framework, opportunities for Surinam, processes and procedures, carbon trade

9.15 – 10.15 Basics of CDM project development
Project cycle
Documents: PDD, PIN, Letter of Approval
Additionality
Methodologies
Baseline- and project scenario
Validation en verification
Small and large scale
Monitoring
10.15 – 10.45 Additionality
Background and principles
Use of the “Tool for the demonstration and assessment of additionality”
Practical exercise in assessing additionality
11.30 – 12.15 Methodologies relevant for Surinam
Emission factors for renewable energy production;
Avoided methane emissions
Practical exercise in calculation of emission factors
13.00 – 13.45 Sustainable development
description in the PDD
connections to national policy
Gold Standard certification
13.45 – 14.30 Drafting PIN and PDD
14.30 – 15.00 Introduction case studies
Based on two concrete case the participants of the workshop analyse a project for CDM aspects. Participants are asked to describe convincingly a number of key issues of a PDD.

 

 

19 June 2008

 

8.00 – 12.00 Discussion of individual project ideas of Surinamese project developers
Rest of day Elaboration of case studies (at home)

 

 

20 June 2008

 

8.00 – 8.30 Registration
8.30 – 9.00 Feedback day 1 and 2
9.00 – 9.30 Progress with the establishment of the CDM Office
organisational framework in Surinam
proposed approval process
9.30 – 11.30
 
Presentation case studies
Participants present de results of the case studies of day 1
11.30 – 12.15 Validation and registration, verification and issuance

processes
Validation and Verification Manual
role of organisations
timing

13.15 – 14.00
 
Bundling small scale projects
regular bundling
Programmes of Activities
opportunities in the voluntary market
14.00 – 14.45 Planning CDM project development
14.45 – 15.00 Evaluation and next steps